Park Pointe Update for week ending November 9th

1. Finalizing solutions regarding in-the-field discovered pipe issues along Amsterdam corridor with SD1. Once resolved, the fill and buttressing along Hamilton and to the south of the planned detention basin will begin. 2. All Stage 2 requirements have been agreed to....