1. Short week due to the New Year holiday and poor weather limited progress this week. 
  2. Working through scope adjustments with SD. 
  3. Duke Energy was working to move power lines to new poles. Targeted to be completed the week of January 6th . 
  4. Spectrum is scheduled to move their lines to the new pools this week. We need all of their lines moved as well so we can get the old poles removed and ramp up the work related to the detention basin. 
  5. Northern Kentucky Water is schedule to begin work on new water main this week.