• Monday 11/9:
    • Bray placed water along Gateway towards Bellavista
    • Bray placed topsoil between curb and sidewalk along Amsterdam
    • Reigler finished curbs along Gateway
    • Sign crew placed caps on the entrance signs
  • Tuesday 11/10:
    • Bray placed water along Bellavista
    • Bray graded around the entrance signs of Park Pointe
    • Landscapers planted trees lower part of Amsterdam Rd.
    • Riegler fine graded Gateway and Vistapointe Dr.
  • Wednesday 11/11:
    • Bray placed water along Bellavista
    • Bray earthwork crew didn’t work because of the rain the night before
    • Riegler paved patches on Amsterdam and Gateway
    • Riegler paved Gateway and Vistapointe Dr.
    • Markesbery prepped for sidewalk on Amsterdam down near orange house.
  • Thursday 11/12:
    • Bray placed water along Bellavista
    • Bray placed storm structures 400 and 401 across Gateway
    • Bray earthwork crew didn’t work because of the rain on Tuesday night
    • Markesbery prepped for sidewalk on Amsterdam down near orange house
    • Duke and NKWD raised services to meet sidewalk grades on Amsterdam
    • Sign crew placed caps on the entrance signs and finished grouting the mortar joints
    • Paul Michels was onsite removing curb/sidewalk along Montague
  • Friday 11/13:
    • Bray placed downspout trunk line in front of Lots 63-67
    • Bray made the connection from CB 801 into SD1 combined sewer at the intersection of Amsterdam Rd. and Montague Rd.
    • Bray graded around the entrance signs of Park Pointe
    • Bray replaced the 3 sided top to CB 604 with a 4 sided top
    • Riegler removed damaged curbs along Amsterdam Rd.
    • Markesbery poured sidewalk on Amsterdam down near orange house
    • Paul Michels was onsite removing curb/sidewalk along Montague
    • Barricades were reset along Amsterdam Rd. for the weekend.