• Monday 11/2:
    • Bray placed storm on Bellavista
    • Bray graded Vistapointe Dr.  since it had rained the previous Thursday and no work could be completed on the previous Friday.
    • Sign crew installed Stone caps on the sign at intersection of Montague/Amsterdam Rd.
  • Tuesday 11/3:
    • Bray placed storm on Bellavista
    • Bray proof rolled the subgrade on Vistapointe Dr.
    • Bray started to clean up rocks along Amsterdam Rd. from the irrigation crews.
    • Landscapers planted trees lower part of Amsterdam Rd.
    • CSA helped by getting the standpipe lowered in the detention pond to start the drying process for Paul Michels.
  • Wednesday 11/4:
    • Bray placed finished the main storm line on Bellavista
    • Bray graded Vistapointe Dr. and prepared for rain.
    • Riegler placed stone on Vistapointe Dr and a small portion of Gateway Dr.
    • Landscapers picking rocks and planting additional trees on Amsterdam Rd.
    • Duke crews were onsite adding anchor lines to a utility pole on Amsterdam Rd.
  • Thursday 11/5:
    • Bray placed downspout trunk line in front of Lots 61 & 62
    • Bray made the connection from CB 801 into SD1 combined sewer at the intersection of Amsterdam Rd. and Montague Rd.
    • Bray graded/topsoiled the ditch along Amsterdam Rd.
    • Riegler poured curb on Vistapointe Dr. & some of Gateway Dr.
    • Landscapers worked on fine grading along the ditech
  • Friday 11/6:
    • Bray placed downspout trunk line in front of Lots 63-67
    • Bray made the connection from CB 801 into SD1 combined sewer at the intersection of Amsterdam Rd. and Montague Rd.
    • Bray graded/topsoiled the ditch along Amsterdam Rd.
    • Riegler poured curb on Vistapointe Dr. & some of Gateway Dr.
    • Landscapers hydro seeded the ditch line along Amsterdam Rd and portions of Park Pointe Dr.
    • Barricades were reset along Amsterdam Rd. for the weekend.