• Monday 10/19:
    • Rained Out No Wok.
  • Tuesday 10/20:
    • Rained Out Limited Work
    • Paul Michels raised Sanitary Manhole 7 in preparation of fine grading the entrance by Bray.
  • Wednesday 10/21:
    • Work site Wet – Limited Work
    • Cincy Cuts Saw cut some areas for Bray, curb cuts for Riegler, as well as along Montague Rd for new curb and sidewalk.
    • Bray replaced the conduit crossover in Gateway drive with Sch. 40 PVC.
    • Duke was onsite and made the last 2 street lights live on Amsterdam Rd.
  • Thursday 10/22:
    • Work Site Wet – Limited Work
    • Bray poured flow lines in the catch basins accessible to the roadways.
    • Riegler’s concrete sub poured an additional section along Amsterdam Rd.
  • Friday 10/23:
    • Bray placed gravel base for driveways aprons along Amsterdam Rd.
    • Riegler’s concrete sub formed sidewalks along Gateway Dr. in preparation to pour on Monday.
  • Saturday 10/24:
    • No Work