• Monday 6/15:  Bray installed DIP san pipe from MH 20 toward MH 21. Bray installed san lateral for lot 53 and back filled. Bray installed 65 ft sanitary pipe along Park Pointe Dr. Paul Michels pipe crews worked for half day on storm line next to circle house along Amsterdam Rd. Bray also placed topsoil along Amsterdam Rd below Hamilton Dr.
  • Tuesday 6/16: Bray installed san lateral for lot 54 and back filled. Bray installed 50 ft sanitary pipe along Park Pointe Dr. Bray installed 50 ft san  pipe from MH 20 toward MH 21 in the Vista Pointe Dr/.  Paul Michels didn’t show up.
  • Wednesday 6/17: Bray installed sanitary pipe between MH 28 and 27 and set up MH 27.  Bray cut the Vista Pointe and pile dirt for sanitary line in vista pointe dr. Bray cut and benched in the south site of the Vista pointe Dr. Bray placed check dam along Amsterdam Rd below Hamilton Dr. P.Michels didn’t show up.
  • Thursday 6/18: Bray back filled pipe between MH 27 and MH28. Bray also installed san lateral for lot 21. Bray placed fill south side of Vista pointe Dr and compacted. Paul Michels didn’t show up.
  • Friday 6/19: Bray back filled pipe san lateral for lot 21. Bray placed fill south side of Vista pointe Dr and compacted. Bray placed fill and compacted between south of Vista pointe Dr and north side of Park Pointe Dr. CSA seeded along Amsterdam Rd between the ditch and edge of the road with erosion control purpose. Paul Michels didn’t show up.