• Monday 7/13: Riegler Placed the 8-in gravel along 550-ft of Amsterdam Rd. Dan & Dennis from City of Park Hills inspected proof roll test and they were fine with road performance. Rigler also placed 6-in DGA for that section of the road. Bray placed fill in between the west side of the Bellavista Dr and east side of HW 704. Bray also back filled the area where they cut for sanitary line. Trimble put the foundation and pour concrete for footer of lot #60. 
  • Tuesday 7/14: Riegler prepared the road for pouring the concrete for Curb and gutter. Bray pipe crew were installing san pipe between MH 27 and 26 (2 sticks off pipe) along Bellavista Dr. Bray also was placing fill in the west side of the Bellavista and east side of HW 704. Paul Michels crew the fixed the silt fence along Gateway Dr and they installed the raiser for old san Manhole in the intersection of Park Pointe Dr and Parkvalle lane.
  • Wednesday 7/15: Riegler pouring concrete for curb and gutter of 550 ft of Amsterdam Rd. Bray pipe crew installed storm pipe between MH 502 and 501. Bray also hauled off the dirt of Vista Pointe Dr and placed in the west side of the Bellavista Dr and east side of the HW 704.
  •  Thursday 7/16: Bray pipe crew back filled storm pipe between MH 502 and 501 and start to install pipe between MH 501 and 500.  Bray also hauled off the dirt of Vista Pointe Dr and placed in the west side of the Bellavista Dr and east side of the HW 704. 
  • Friday 7/17: Bray pipe crew installed the storm pipe along Vista pointe Dr. Bray worked  on the final grading of the north side of the Vista Pointe Dr.