• Monday 8/31: Bray’s pipe crew installed 2 sanitary laterals for lots 29 & 30. They were 73′ each. Dirt crew demoed blacktop on Amsterdam and backfilled behind retaining wall.
  • Tuesday 9/1: Bray pipe crew installed 133′ of 18″ storm pipe and set MH 413 and started to backfill. Brays’ dirt crew hauled off concrete from Amsterdam Rd. A&A planted trees along Amsterdam Rd.
  • Wednesday 9/2: Bray’s pipe crew installed 51’ of 8” sanitary pipe and set up MH 24. They also installed 6” sanitary lateral along Vista Pointe Dr. A&A planted trees along Amsterdam Rd.
  • Thursday 9/3: Rained out.
  • Friday 9/4: Rained out