• Monday 9/21: Bray’s pipe crew installed lateral #4 to main and backfilled. They also installed CB 606. Dirt crew cut Park Point Dr to subgrade. Riegler was installing underdrain on upper Amsterdam and placing #2 stone.
  • Tuesday 9/22: Bray’s pipe crew installed sanitary line along Bellavista Dr and lateral for lot #3. Bray placed to fill in Vista pointe Dr.McD installed rebar for the footer of the sign in the north of Park Pointe Dr. Bray finished final grading Park Ponte Dr. A&A watered the grass in the hillside of Amsterdam Rd and they spread temporary seed along Park Pointe Dr and Gateway Dr.
  • Wednesday 9/23: McD concrete poured concrete for ParkHills signs and the entrance sign in the south side of Park Pointe Dr. Bray’s pipe crew installed lateral for Lot #1 and backfilled. Bray placed fill along Vista Pointe Dr. Abercrombie laid out Park Pointe Dr. Riegler finished placed DGA along the south side of Amsterdam Rd.
  • Thursday 9/24: Bray graded Bellavista Dr. McD poured concrete the entrance sign in the north of Park Pointe Drive. Abercrombie laid out the curb location and elevation of Amsterdam Rd. for the Riegler; A&A planted trees along Amsterdam Rd, and Bray placed topsoil along Amsterdam Rd. next to the detention pond.
  • Friday 9/25: Riegler strung the curb to be poured by concrete on next Monday. Bray crew didn’t work on Friday.