• Monday 9/7: Labor Day (no work)
  • Tuesday 9/8: Bray’s pipe crew installed 84′ of 8″ going to MH 18 and pothole on the upper part of Amsterdam. CSA installed 2 crossovers on the lower part of Amsterdam for Street lights. A&A seed and straw Amsterdam Rd. Riegler from 300 ft of sidewalk along Amsterdam Rd. Bray’s dirt crew cut and fill Vistra point
  • Wednesday 9/9: Bray’s pipe crew tied sanitary into MH 14 and pothole on Amsterdam. Dirt crew cut and fill on Vistra Point. Riegler had to reform the sidewalk to 5′ away from curb.A&A seed & straw and plant trees.
  • Thursday 9/10: Bray’s pipe crew installed CB 600 & 601B and 12″ pipe they also installed MH18  and backfill. Dirt crew cut and fill on Vistra Point. Riegler formed sidewalks along Amsterdam Rd. A&A plant trees and seed and straw. CSA installed crossovers on the lower part of Amsterdam for Amsterdam Rd’s Street lights.
  • Friday 9/11: Bray’s pipe crew installed CB 601 & 602A and install lateral for lot 46. Dirt crew cut and fill on Vistra Point and topsoil behind wall Riegler poured sidewalks along Amsterdam Rd. A&A plant trees and seed and straw. CSA installed crossovers on the lower part of Amsterdam for Amsterdam Rd’s Street lights.