• Monday 7/6: Paul Michels did haul of the junk material all old pipe for behind the circle house. They cleaned the area and they did final grade. Bray was hauling off the concrete along Amsterdam Rd 46 loads. and Pipe crew were working on sanitary line along Vista Pointe Dr. Bray also started to dig lot #60.

 

  • Tuesday 7/7: Bray kept continue grading Amsterdam Rd first section. Bray flow fill sanitary line in Amsterdam Rd for Paul Michels with 3CY CDF. Pipe crew were working on sanitary line along Vista pointe Dr. Bray also finished digging lot #60. Jeremy and Mehdi seeded the hill between Amsterdam Rd and Hamilton Dr.

 

  • Wednesday 7/8: Bray worked on the back fill the trench for sanitary line along Vista Pointe Dr.  Bray placed fill between west side of the Bellavista Dr and east side of the HW 704. Paul Michels worked for half a day on flowing fill the old sanitary line along Amsterdam Rd. Cincinnati Bell contractor raised 2 CBT manholes along Amsterdam Rd. Bray raised the elevation of two catch basins 701 and 702.

 

  • Thursday 7/9: Bray worked on the back fill the trench for sanitary line along Vista Pointe Dr.  Bray placed fill between west side of the Bellavista Dr and east side of the HW 704. City of park hills’ inspectors (Dan and Dennis) showed up for proof roll test along Amsterdam Rd and some spots needs to be reinforced before placing stones. Riegler started to install 6″ under drain pipes in both sides of the Amsterdam Rd. Paul Michels raised old existing brick manhole close to the intersection of the Park Pointe Dr and Amsterdam Rd.

 

  • Friday 7/10: Riegler started at 7:30 AM. They dog the bad spots along Amsterdam Rd and back filled with #2’s. They installed fabric and geo grid at 450-ft section of Amsterdam Rd. They also placed gravel for 1/3 of road before rain started at 9AM. Bray crew and Reigler left the job site after rain. Bray pipe crew were working on sanitary line along Vista Pointe Dr.